BlueAndGold.ca is a website dedicated to the development of the new Blue Bomber Stadium that will be located at the University of Manitoba. The stadium will hopefully be opening for the 2011 season.

If you missed it before, here are photos of the new stadium designs and what it should look like when it is completed in 2011.

The facility will be a world-class athletic and recreation venue including the home of the Blue Bombers and Bisons.

Stadium Timeline:

* Final stadium architectural and engineering design process – immediate
* New stadium site preparation and landscaping work – fall 2009
* Shovels in ground on new stadium – spring 2010
* Construction of phase 1 retail at existing site – spring 2010
* Stadium construction substantially complete – spring 2011
* Demolition of existing stadium site and construction of phase 2 retail – spring 2011
* Opening of new stadium – football season 2011
* Substantial completion of phase 3 retail at existing site – summer 2013