Just in time for the fall weather, the skywalk between the Delta Winnipeg Hotel and RBC Winnipeg Convention Centre will reopen.


The skywalk has been closed since April 9, 2015 due to a need for an assessment of the connection to the Convention Centre. Assessment has since been conducted and completed, and repair work has progressed.

Repairs to the skywalk will be ongoing but the majority of the skywalk will finally reopen to the public early this week. Shoring supports have been installed to allow the skywalk to safely open to the public.

During the construction phase, the RBC Convention Centre will only be accessible through the skywalk during the Centre’s operating hours. Barricades and signage will be in place to notify users that there is no access to the east side of the skywalk during Winnipeg Convention Centre after-hours.

There may be temporary skywalk closures throughout the season to complete construction.